Investment Program

Investment Program

Investment program execution 2020-2025

As of 1 January 2026, CAEPCO JSC's share of the national totals is:

  • Installed capacity — 1,306 MW (5.0%)
  • Power generation by thermal power plants — 6.1 bn kWh (6.3%)
  • Renewable power generation — 0.32 bn kWh (3.7%)

Between 2020 and 2025, the power-generating companies of CAEPCO JSC completed the following major measures under their investment programmes:

2021

  • Reconstruction of the air heater cubes of boiler unit No. 2
  • Expansion of the ash dump’s second queue

2023