Petropavlovsk Heat Networks LLP during the press tour on the objects of reconstruction and modernization of the company told the public about the work carried out on the eve of the next heating season.
The event was organized with the purpose of informing consumers of heating energy about using the costs set in the tariff estimate for the regulated service, as well as on the execution of investment programs and modernization of the company's assets.
As part of the capital and current repairs in 2018, the company plans to replace 11,984 km of heating networks (of which 4,310 km are backbone networks and 7,674 km are distribution networks). As of August 14, 2018, the pipeline was replaced by a total length of 8,800 km (backbone networks - 3,689 km, distribution networks - 5,111 km). The percentage of fulfillment of the annual repair plan is 73.74%. The amount of the repair fund for 2018 is 444.07 million tenge, excluding VAT.