Power Machines, Toshiba JV. High voltage transformers LTD ("Power Machines" JV and Toshiba) will supply two transformers for the reconstruction and modernization of the substation Pavlodar CHP-3.
The Equipment’s Customer is Pavlodarenergo JSC , a part of Central Asian Electric Power Corporation (CAEPCO). According to the contract’s terms the JSC will design, manufacture and supply two transformers of 110 kV voltage class 80 MVA each. The joint venture will provide installation supervision and customer training as well.
Delivery deadline is the third quarter of 2015. This is going to be a first project of a joint venture in the CIS energy market.