During 2015 AEDC JSC continues implementation of projects under the investment program. High operational reliability and long service life of the new equipment will ensure fault-free operation of facilities and the uninterrupted supply of power to consumers.
Currently, work is underway on the reconstruction of 110/35/10 kV substation “Novoaleksandrovka” Arshaly District, which has been already installed and commissioned a new gas-insulated switchgear Alstom to replace the old oil type MKP-110 kV. Also, installations of the ground loop is produced under the new Modular building of 10 kV metal-clad switchgear and edit a foundation base for the cells 10 kV. “We are planning to replace oil switch gears MKP-110 kV with electric gas ones from Alstom and the works on SS 110/35/10 kV” Vishnevka” in district Arshaly are scheduled for the beginning of September”, - stated Nikolay Lamonov, chief engineer of the Akmola MES.